Road map to the design process for extension |
---|
High level review of the country to identify potential areas suitable for wind energy assessment | A Project Study Area was identified |
---|---|
Environmental & other constraints were identified |
Site specific surveys are carried out on a preliminary layout to ground truth the information available | Site specific surveys and studies were undertaken |
---|---|
A design layout emerged of this project | |
The initial design layout of this project consisted of 8 Turbines |
Consultation commenced with the public, local authorities and interested parties based on the design layout | The design layout was presented to the public, local authorities and other interested parties and feedback was received on various aspects of the project |
---|
Surveys & Design | Feedback from meetings with the public and other interested parties informed the design team and influenced the path of the project |
---|---|
Detailed site specific studies and surveys were carried out including ground investigations, ecology, noise, hydrology, human environment, archaeology, landscape etc. These surveys will continue throughout the design process | |
A Technical appraisal was carried out | |
Discussions with the local community continued throughout the design process |
Design Review - Interpretation and incorporation of information gathered & Ongoing Consultation | Information from the detailed site specific surveys, technical appraisals and all feedback from consultation with the public, local authorities and interested parties was taken into consideration |
---|
Current Stage of Design |
---|
Assessment and ongoing consultation | Public consultation is ongoing |
---|---|
An EIAR is being prepared and technical appraisals are being finalised | |
A final planning layout will emerge from this process |
Prepare & Submit Planning Application | A Planning Application and accompanying Environmental Impact Assessment Report. |
---|